Naval Air Station Jacksonville Patrol Road Restoration

Naval Air Station Jacksonville Patrol Road Restoration

Project currently under way and expected to be completed in fall of 2013•Includes nearly 1 mile of full depth road way reconstruction

Nearly 2,000 feet of concrete ditch paving

1.5 miles of 18-24 inch concrete storm drainage pipe

Includes ½ acre of 20 foot deep pond dug in an area that has irregularly bad ground water

The Navy Requires that the road remain open and accessible for vehicle traffic as well as pedestrian traffic through out the entire duration of the project

The Navy also requires that every safety measure possible be taken and utilized at all times. Any violation of this policy results in a company\'s expulsion from the project.

Project totaled $1.8 million and is scheduled to be completed in the fall of 2013 taking a total of 4 months